South Cape Construction Update

Construction is underway in the block from 10th Place to 11th Place.
 
The Project team has demolished sidewalk and curb ahead of schedule and is quickly installing the water main line from 10th Place to 11th Place.
 
Our crews are progressing quickly and installing roughly 100 linear feet of water main each day, weather permitting.

Crews install the water main from 9th Place to 10th Place

 
 
 
 
 
 
 
 
 
 
 
 
 
 
As we work in this block, please remember to access businesses from north of the Club Square Parking Lot. Use businesses’ rear and side entrances when possible to access businesses in the block, including Big Blue Brewing, Rack ‘Em Spirits & Times, Rockade, and Dixie Roadhouse. For Dollar Tree, access from Cape Coral Parkway.
Patrons can park in Club Square or along street parking on 11th Place.
 
Detours will be in place, and the easiest route for customers to access businesses in the block from 10th Place to 11th Place is to use the intersection at 46th Lane and 10th Place to enter Club Square Parking Lot from the north.

Crews will do their best to work around the busiest days and hours of operation.

 

The crews have progressed past Big Blue Brewing and continue to make gains to reach Dixie Roadhouse soon.
 
Next, crews will progress the water main line construction to the block from 11th Place to Vincennes Boulevard.
 
Crews will dig up the site and will re-establish the path as quickly as they can. The following day, they will dig up the site to install the water main. By the end of each business day, crews will grade the work site and restore it to re-establish access to driveways and business entrances.
 

 

Crews back-fill and grade the construction area to create a temporary pathway at the end of the workday.
 
For more information on the project visit www.se47terrace.com